By looking at Page 2 of Scenario 2, if nothing else changes on the project, will the project finish sooner than the baseline, at the same time as the baseline, or after the baseline?
Group of answer choices
It cannot be determined
After the baseline
At the same time as the baseline
Sooner than the Baseline
Flag question: Question 2
Question 2 2 pts
By looking at Page 3 of Scenario 1, how many -actionable tasks- that are on the critical path have a resource assigned that is fully utilized (HINT: is working at 100%).
Group of answer choices
4
3
2
1
Flag question: Question 3
Question 3 2 pts
By looking at Page 2 of Scenario 1, which is the 2nd MOST expensive phase of the project?
Group of answer choices
It cannot be determined
Planning
Executing Activities
Initiating Activities
Monitoring & Controlling
Executing
Planning Activities
Closing
Initiating
Closing Activities
Flag question: Question 4
Question 4 2 pts
By looking at Page 2 of Scenario 2, how many -actionable tasks- that are NOT ON the critical path are STILL IN alignment with the baseline?
Group of answer choices
6
10
8
11
Flag question: Question 5
Question 5 2 pts
By looking at Page 1 of Scenario 2, how many UNIQUE resources have -actionable tasks- that they are assigned to that are NOT ON the critical path? (HINT: don't count the tasks, and don't count any resource more than once.)
Group of answer choices
4
5
2
3
Flag question: Question 6
Question 6 2 pts
By looking at Page 2 of Scenario 1, which PHASE of the project has resources that are OVER ALLOCATED?
Group of answer choices
Initiating Activities
Planning Activities
Monitoring & Controlling
It cannot be determined
Planning
Executing Activities
Closing Activities
Executing
Initiating
Closing
Flag question: Question 7
Question 7 2 pts
By looking at Page 1 of Scenario 1, how many -actionable tasks- have multiple predecessors?
Group of answer choices
4
1
3
2
Flag question: Question 8
Question 8 2 pts
By looking at Page 1 of Scenario 2, is the OVERALL project currently ahead of schedule, behind schedule, or on schedule?
Group of answer choices
It cannot be determined
On Schedule
Ahead of Schedule
Behind Schedule
Flag question: Question 9
Question 9 2 pts
By looking at Page 2 of Scenario 2, how many -actionable tasks- have had some progress made on them?
Group of answer choices
11
10
9
8
Flag question: Question 10
Question 10 2 pts
By looking at Page 3 of Scenario 1, how many -actionable tasks- are NOT on the critical path [HINT: Milestone tasks are also on the critical path].
Group of answer choices
10
15
9
8
Flag question: Question 11
Question 11 2 pts
By looking at Page 1 of Scenario 1, how many -actionable tasks- have a -Start to Start- relationship with another task?
Group of answer choices
3
2
1
4
Flag question: Question 12
Question 12 2 pts
By looking at Page 2 of Scenario 2, is the OVERALL project currently over budget [spending too much], under budget [spending too little] or on budget.
Group of answer choices
Under budget
On budget
Over budget
It cannot be determined
Flag question: Question 13
Question 13 2 pts
By looking at Page 1 of Scenario 2, how many -actionable tasks- are NOT ON the critical path and have made some progress?
Group of answer choices
2
4
3
5
Flag question: Question 14
Question 14 2 pts
By looking at Page 1 of Scenario 1, how many -actionable tasks- have ALL of the resources assigned to that task that are fully utilized [100%]?
Group of answer choices
10
11
6
8
12
Flag question: Question 15
Question 15 2 pts
By looking at Page 2 of Scenario 1, which resource COSTS the least on the total project?
Group of answer choices
QC 2
Analyst 1
Designer 2
Driver 3
Driver 1
QC 3
Project Mgr
QA 1
QC 1
QA 2
Driver 2
Designer 1
Project Admin
Analyst 2
QA 3
Flag question: Question 16
Question 16 2 pts
By looking at Page 2 of Scenario 1, how many resources are NOT OVER ALLOCATED?
Group of answer choices
It cannot be determined
12
15
10
Flag question: Question 17
Question 17 2 pts
By looking at Page 1 of Scenario 1, how many -milestone- tasks are shown on this page for the project?
Group of answer choices
2
4
3
1
Flag question: Question 18
Question 18 2 pts
By looking at Page 1 of Scenario 1, how many -actionable tasks- have a -Finish to Start- relationship with another task?
Group of answer choices
12
18
14
16
Flag question: Question 19
Question 19 2 pts
By looking at Page 3 of Scenario 2, how many -actionable tasks- that are ON the critical path ARE IN alignment with the baseline?
Group of answer choices
1
3
4
2
Flag question: Question 20
Question 20 2 pts
By looking at Page 3 of Scenario 1, how many -actionable tasks- are on the critical path [HINT: Milestone tasks are also on the critical path].
Group of answer choices
15
12
5
7
Flag question: Question 21
Question 21 2 pts
By looking at Page 3 of Scenario 2, how many -actionable tasks- that are ON the critical path are NOT in alignment with the baseline?
Group of answer choices
1
2
0
3
Flag question: Question 22
Question 22 2 pts
By looking at Page 1 of Scenario 2, is the OVERALL project currently over budget [spending too much], under budget [spending too little] or on budget.
Group of answer choices
Over Budget
On Budget
It cannot be determined
Under Budget
Flag question: Question 23
Question 23 2 pts
By looking at Page 2 of Scenario 1, which resource does the LEAST amount of work?
Group of answer choices
Designer 1
QA 3
Driver 1
QC 3
Analyst 2
QA 1
Analyst 1
Project Admin
QC 2
Driver 3
Designer 2
Project Mgr
Driver 2
QC 1
QA 2
Flag question: Question 24
Question 24 2 pts
By looking at Page 2 of Scenario 1, which is the MOST expensive phase of the project?
Group of answer choices
Initiating Activities
Monitoring & Controlling
Planning
Initiating
Executing Activities
Closing
Planning Activities
It cannot be determined
Closing Activities
Executing
Flag question: Question 25
Question 25 2 pts
By looking at Page 3 of Scenario 1, how many -actionable tasks- that are NOT on the critical path have a resource assigned that is fully utilized (HINT: is working at 100%).
Group of answer choices
8
10
12
6
Flag question: Question 26
Question 26 2 pts
By looking at Page 1 of Scenario 2, how many UNIQUE resources have -actionable tasks- that they are assigned to that are ON the critical path? (HINT: don't count the tasks, and don't count any resource more than once.)
Group of answer choices
2
4
3
1
Flag question: Question 27
Question 27 2 pts
By looking at Page 3 of Scenario 2, how many -actionable tasks- that are NOT ON the critical path are NOT in alignment with the baseline?
Group of answer choices
1
3
4
2
Flag question: Question 28
Question 28 2 pts
By looking at Page 2 of Scenario 2, is the OVERALL project currently ahead of schedule, behind schedule, or on schedule?
Group of answer choices
Ahead of Schedule
It cannot be determined
Behind Schedule
On Schedule
Flag question: Question 29
Question 29 2 pts
By looking at Page 1 of Scenario 1, how many -unique resources- are assigned to the -actionable tasks-? (Hint: Don't count the number of -tasks- and don't count any resource more than once.)
Group of answer choices
6
10
15
8
Flag question: Question 30
Question 30 2 pts
By looking at Page 1 of Scenario 1, how many -actionable tasks- have a -Start to Finish- relationship with another task?
Group of answer choices
1
4
2
0
3
Flag question: Question 31
Question 31 2 pts
By looking at Page 3 of Scenario 1, how many UNIQUE resources have -actionable tasks- that they are assigned to that are ON the critical path? (HINT: don't count the tasks, and don't count any resource more than once.)
Group of answer choices
3
2
1
4
Flag question: Question 32
Question 32 2 pts
By looking at Page 1 of Scenario 1, how many -actionable tasks- have a -Finish to Finish- relationship with another task?
Group of answer choices
4
1
3
2
Flag question: Question 33
Question 33 2 pts
By looking at Page 1 of Scenario 1, how many -actionable tasks- have no predecessors?
Group of answer choices
2
1
4
3
Flag question: Question 34
Question 34 2 pts
By looking at Page 2 of Scenario 2, how many -actionable tasks- that are NOT ON the critical path are now NOT in alignment with the baseline?
Group of answer choices
0
4
1
3
2
Flag question: Question 35
Question 35 2 pts
By looking at Page 2 of Scenario 2, how many -actionable tasks- that are ON the critical path are STILL IN alignment with the baseline? (HINT: milestone tasks are also on the critical path and are always in alignment with the baseline.)
Group of answer choices
1
3
4
2
Flag question: Question 36
Question 36 2 pts
By looking at Page 1 of Scenario 1, how many -actionable- tasks are shown on this page for the project?
Group of answer choices
17
14
15
16
Flag question: Question 37
Question 37 2 pts
By looking at Page 2 of Scenario 1, which phase of the project is the MOST number of days?
Group of answer choices
Closing Activities
It cannot be determined
Planning Activities
Initiating
Closing
Initiating Activities
Executing Activities
Executing
Planning
Monitoring & Controlling
Flag question: Question 38
Question 38 2 pts
By looking at Page 1 of Scenario 1, how many -actionable tasks- have multiple resources assigned?
Group of answer choices
5
2
7
3
Flag question: Question 39
Question 39 2 pts
By looking at Page 1 of Scenario 2, how many -actionable tasks- are showing progress but considered -ahead of schedule-?
Group of answer choices
1
4
2
3
Flag question: Question 40
Question 40 2 pts
By looking at Page 2 of Scenario 1, how many resources do the EXACT same amount of work?
Group of answer choices
2
5
4
3
Flag question: Question 41
Question 41 2 pts
By looking at Page 2 of Scenario 1, which resource is the most expensive, based on their -Standard Hourly- rate?
Group of answer choices
Designer 2
Driver 2
Analyst 1
QA 2
QC 2
QC 3
Designer 1
QC 1
Project Mgr
Driver 3
Analyst 2
Driver 1
QA 3
Project Admin
QA 1
Flag question: Question 42
Question 42 2 pts
By looking at Page 1 of Scenario 2, how many -actionable tasks- are showing progress but are still considered -behind schedule-?
Group of answer choices
3
1
2
4
Flag question: Question 43
Question 43 2 pts
By looking at Page 3 of Scenario 2, and comparing it to Page 2 of Scenario 2, is the OVERALL project MORE over budget or under budget, LESS over budget or under budget, or at the same -budget indication- as on Page 2 of Scenario 2?
Group of answer choices
More over or under budget
Same indication as on Page 2
Less over or under budget
It cannot be determined
Flag question: Question 44
Question 44 2 pts
By looking at Page 2 of Scenario 1, how many resources have the same -total cost- on the project?
Group of answer choices
3
2
4
It cannot be determined
Flag question: Question 45
Question 45 2 pts
By looking at Page 3 of Scenario 2, if nothing else changes on the project, will the project finish sooner than the baseline, at the same time as the baseline, or after the baseline?
Group of answer choices
It cannot be determined
Sooner than the Baseline
At the same time as the Baseline
After the Baseline
Flag question: Question 46
Question 46 2 pts
By looking at Page 2 of Scenario 1, which is the LEAST expensive phase of the project?
Group of answer choices
Executing
It cannot be determined
Planning Activities
Closing
Executing Activities
Closing Activities
Initiating
Planning
Initiating Activities
Monitoring & Controlling
Flag question: Question 47
Question 47 2 pts
By looking at Page 2 of Scenario 1, which resource COSTS the most on the total project?
Group of answer choices
Analyst 1
QA 2
Driver 3
Analyst 2
QC 2
Project Admin
QA 1
Project Mgr
Driver 2
Designer 1
QC 1
QA 3
QC 3
Designer 2
Driver 1
Flag question: Question 48
Question 48 2 pts
By looking at Page 2 of Scenario 1, which PHASE of the project has resources that are NOT OVER ALLOCATED?
Group of answer choices
It cannot be determined
Initiating Activities
Closing
Initiating
Executing
Planning Activities
Planning
Monitoring & Controlling
Closing Activities
Executing Activities
Flag question: Question 49
Question 49 2 pts
By looking at Page 3 of Scenario 1, how many -actionable tasks- that are on the critical path have a resource assigned that is NOT fully utilized (HINT: not working at 100%).
Group of answer choices
2
4
1
3
Flag question: Question 50
Question 50 2 pts
By looking at Page 2 of Scenario 1, which phase of the project is the LEAST number of days?
Group of answer choices
Closing Activities
Initiating Activities
Executing Activities
It cannot be determined
Initiating
Monitoring & Controlling
Planning
Executing
Closing
Planning Activities
Flag question: Question 51
Question 51 2 pts
By looking at Page 1 of Scenario 2, how many -actionable tasks- are ON the critical path and are NOT completed?
Group of answer choices
5
3
2
4
Flag question: Question 52
Question 52 2 pts
By looking at Page 2 of Scenario 1, how many resources are OVER ALLOCATED?
Group of answer choices
4
3
In cannot be determined
2
Flag question: Question 53
Question 53 2 pts
By looking at Page 3 of Scenario 2, how many -actionable tasks- that are NOT ON the critical path ARE IN alignment with the baseline?
Group of answer choices
3
4
2
1
Flag question: Question 54
Question 54 2 pts
By looking at Page 3 of Scenario 1, how many UNIQUE resources have -actionable tasks- that they are assigned to that are NOT ON the critical path? (HINT: don't count the tasks, and don't count any resource more than once.)
Group of answer choices
1
4
3
2
Flag question: Question 55
Question 55 2 pts
By looking at Page 2 of Scenario 2, how many -actionable tasks- that are ON the critical path are now NOT in alignment with the baseline? (HINT: milestone tasks are also on the critical path and are always in alignment with the baseline.)
Group of answer choices
2
3
4
1
Flag question: Question 56
Question 56 2 pts
By looking at Page 3 of Scenario 2, and comparing it to Page 2 of Scenario 2, is the OVERALL project MORE ahead or behind schedule, LESS ahead or behind schedule, or at the same -schedule indication- as on Page 2 of Scenario 2?
Group of answer choices
More ahead or behind schedule
It cannot be determined
Less ahead or behind schedule
Same indication as on Page 2
Flag question: Question 57
Question 57 2 pts
By looking at Page 3 of Scenario 1, how many -actionable tasks- that are NOT on the critical path have a resource assigned that is NOT fully utilized (HINT: not working at 100%).
Group of answer choices
3
2
4
1
Flag question: Question 58
Question 58 2 pts
By looking at Page 2 of Scenario 1, how many resources are the least expensive, based on their -Standard Hourly- rate?
Group of answer choices
6
4
5